Maldives Transport and Contracting Company (MTCC) has completed the casting work for the road development project in Hoarafushi, Haa Alifu Atoll.
MTCC stated that the installation of the electrical junction box and pipe-laying work for the project is at 83% and 36% completion respectively, while curbstone installation works are now ongoing. The scope of the road development project includes the construction of 11 roads measuring 5.3km in length, construction of a 25,909sqm carriageway, installation of an 11,114sqm pavement, and the installation of a stormwater infiltration system, streetlights, and road markings.
MTCC commenced the road development project in Hoarafushi in January. The state-owned company is tasked with completing the project within 470 days at a cost of USD4.6 million.